Phasing

It is planned to build the core network in three phases, with each phase being of approximately 12 months duration. The phasing proposals are:

Phase 1
May '02 to
June '03

Phase 2
June '03 to June '04

Phase 3
June '04 to June '05

Coachman’s Drive Link

Southgate Avenue

Hazelwick Avenue

Southgate Avenue

Haslett Avenue East

Gatwick Road

Station Way

Tushmore Roundabout

Horley North

The Boulevard

London Road

Longbridge Roundabout

High Street

Manor Royal

Horley South

The Beehive (City Place)

Faraday Road

 

Gatwick South Terminal

Fleming Way

 

 

Gatwick North Terminal

 

 

 Gatwick Cargo

 


This programme will enable initial Fastway services to start in Summer 2003