Location: Ministry Home > Traveller's Information > Highway 69 > Status of Construction Activity

Status of Construction Activity

A: Recently Completed Projects
Location Length Date Opened
Musquash Road 32/38 to Musquash River 4 km October 1999
Badger Road to Seguin River (Parry Sound Bypass) 10 km November 2001
Highway 141 to Badger Road 4 km October 2002
MacTier to Highway 141 26 km October 2003
Interchange at Muskoka Roads 32 and 38 -- October 2005
Interchange at Gladu Road 2.4 km April 2006 (to be opened with Highway 537 to Sudbury)
Old Wanup Road underpass 0.6 km May 2006 (to be opened with Highway 537 to Sudbury)

B: Projects Currently Under Construction
Location Length Planned Opening Date
Musquash River to MacTier. Construction started December 2004 8 km Fall 2007
Parry Sound to Nobel. Construction started June 2005 7 km Fall 2008
Highway 537 to Sudbury (three separate contracts). Construction started January 2005. 9 km Fall 2009

C: Projects Currently In Planning / Engineering / Property Acquisition
Location Length
From South of Nobel to Highway 559 10 km
Highway 559 to Highway 522 68 km
Highway 522 to Highway 64 25 km
Highway 64 to Estaire 22 km
Estaire to Highway 537 11 km