NASA will build Rollercoaster for Ares I escape

NASA will build Rollercoaster for Ares I escape
© NASA via L2 Presentation
 

Get in-depth information at NASASpaceFlight.com's Level 2

Full Story

The full presentation from which this article was based is available for download on L2. Other associated L2 resources listed at the end of this article.

**ARES I / ORION LIVE UPDATE PAGES**

**ARES V / Mars Transport Vehicle (MTV) LIVE UPDATE PAGES**


The process will likely take around a year before the winning vendor is awarded the deal, although that is well within the new timelines Constellation now have to work under, following the decision to halt any work on Pad 39B until 2008, given its requirement to host a LON (Launch On Need) Shuttle flight, in support of STS-125's mission to re-service Hubble.

Despite continued talk of serious issues relating to the development of the Ares I Crew Launch Vehicle, work is still pressing ahead at a pace, in order to have the required infrastructure in place for the vehicle.

In relation to the Ares I-1 test flight, a meeting will take place next week at Constellation KSC (Kennedy Space Center) to discuss the best way forward with pad infrastructure impacts from last week's announcement of the Hubble servicing mission, with LON support.

Minotaur

In other news, Orbital Sciences Corporation's Minotaur rocket will be in use at White Sands for Ares I testing of the LAS (Launch Abort System). Unlike the Little Joe tests ahead of the Apollo era, it will be used to test the tower - as opposed the capsule.

Previous Trade Study - taken from our September exclusive on the trade study

Back to the decision to move forward with the Rollercoaster system, the winner design did have competition from a number of other concepts during the trade study.

During the trade study, detailed analysis was performed on the following system elements: Ingress/egress routes for Pad flight and Ground Support Equipment (GSE) configurations. Operational tasks with associated manloading. Operations hazard levels and flight/closeout/contingency ground crew personnel emergency egress route criteria.

Previous studies for Shuttle and Apollo were used as guidelines, such as the Shuttle's slidewire baskets to a bunker away from the pad, and Apollo's high speed elevators to a blast room.

In total, four major concepts were put forward as Ares EES candidates: 1) Four to six separate four-man cab slide-wire systems to the safety bunker from the Fixed Service Structure (FSS) or Mobile Launcher (ML) tower. 2) Four separate four-to-six man car rail (rollercoaster) systems to the safety bunker from FSS or ML tower. 3) Elevator system to Pad Terminal Connection Room (PTCR) to blast room from FSS or ML tower. 4) Slide-tube system to safety bunker from FSS or ML tower.

The study defined the options as follows:

Slide-wire System:

'A slide-wire system will be used from the crew access arm level of the ML tower or FSS to a bunker located on the west side of the pad. One basket will be attached to each slide wire and have a four person capacity.

'This system will be start from the crew access arm level of the ML tower or FSS and terminate at a bunker located on the west side of the pad just outside of the perimeter fence.'

Rail Car (Rollercoaster) System:

'An unpowered fixed single-rail system from the access arm level of the ML tower to the existing bunker would be used. The railcars could be enclosed to provide personnel protection. Each railcar can hold four to six people.

'The rail would follow the ML tower vertically down to the pad surface, then turn and continue close to the ground to the safety bunker. A passive magnetic and friction braking system will decelerate the cars at the track’s end as well as prevent the cars from hitting each other.'


High Speed Elevator Alternative:


'The egress route would be across the access arm, down the high-speed elevators, into the slide tube, and then into the existing blast room beneath the pad.'

Slidetude System:

'A fixed slide tube made of either metal or hard plastic/fiberglass will extend from the access arm level of the ML tower or FSS to the existing bunker located on the west side of the pad.

'The egress route will be across the access arm to the slide tube, down the slide tube to the bunker, and into the bunker. Each person would enter the tube one at a time from the crew access level on the tower and slide the distance to the bunker.'

The study listed its recommendations for the best EES option as the Rollercoaster/Rail Car system, despite it being the most expensive system - ranking it both first and second (from the RSS and the ML Tower), beating out the Slidewire, Elevators and Slidetube systems.

Further fine tuning and modifications to the designs are expected, with the Rollercoaster cars likely to be semi - or fully - enclosed, to protect escaping crew and/or workers from being sent into the path of an event, such as a hypergolic leak - which would be a serious issue if they weren't enclosed in the cars.

Also relevant to the final design will be the call for a 'clean pad' - which would have impacts on such EES concepts.

The schedule calls for the fabrication of the design to start at the start of 2008 (pending Hubble LON flight target launch date requirement), ready for installation into the pad in 2009.

Other L2 Resources For Ares I, V and Constellation: Ares I-1 Test Flight Plan (full outline) Presentation. ARES I Reference Trajectory. Boeing's STS to Ares - Lessons Learned Presentation. Latest Ares I and Ares V baseline Configuration image and data. CLV DAC-1C (Changes to CLV Upper Stage).

Ares I-1: Four Seg+Dummy 'Tuna Can' stage. Ascent Developmental Flight Test Presentation. CLV Pad 39B Handover Info and Latest. New images of CLV on top of new MLP and LUT. Lockheed Martin CEV/Orion Updates. Constellation news updates. ATK figures on the 5-Seg Booster weight for CLV. 90 Minute Video of Constellation all hands meeting. CLV TIM Meeting Information. CLV/CaLV Infrastructure, Timelines and Information.

CEV-CLV Design Analysis Cycle Review (DAC-2) Presentation. Constellation SRR updates. CLV Stick - Troubleshooting/Alternatives/Updates. New CEV Images (include abort mode). Flight Design and Dynamics Division CEV update. CLV Mono-propellant RCS system. CEV pressurisation system review. CLV/CEV Configuration Images. The 2x3 Seg SRB Crew Launch Vehicle Option Presentation...plus more.






**NASASpaceflight.com Job Opportunities** 