Home | Search | Fraud Prevention | Get Email Updates | Related Links | Media Center | Information Library | Contact Us | About the Site
Lower Manhattan - Information to Build On
Search > Advanced Search
 
Recommended Favorites
> Get Email Updates
> Construction Contacts
> Latest Advisories
> Visualization Tour
> Rebuilding Timeline
> About Lower Manhattan
Project Updates Printer Friendly Version
Fiterman Hall « back
Summary | Daily Activities | Contact Info | FAQs | Links

 Fiterman Hall

Fiterman Hall, located at 30 West Broadway between Barclay and Park Place, was damaged in the September 11, 2001, attack on the World Trade Center (WTC) when falling debris from 7 World Trade Center left it with significant damage in its south façade. The 15-story building, constructed as an office building in the 1950s, had served as an extension of the 199 Chambers Street campus of the Borough of Manhattan Community College (BMCC) since 1993. 


Summary

BMCC is part of the City University of New York (CUNY), which is working with the Dormitory Authority of the State of New York (DASNY) to decontaminate, deconstruct, and rebuild Fiterman Hall. For more than 30 years, CUNY and DASNY have been partners in new construction, renovation, and historic rehabilitation of CUNY buildings.

By September 11, 2001, DASNY and CUNY had virtually completed a total rehabilitation of Fiterman Hall, including extensive asbestos abatement. After September 11th, the City of New York, DASNY, CUNY, and others took steps to clean out some of the debris, close breaches in the south façade, and stabilize the structure. Because mold and WTC dust contaminated the building and rendered it uninhabitable, Fiterman Hall must be taken down and reconstructed. Funding for the decontamination, deconstruction, and rebuilding is coming from sources that include the New York State and City budgets, the Lower Manhattan Development Corporation, the September 11th Fund, and a property insurance settlement.

The project team remains committed to the safe and efficient deconstruction and rebuilding, working with regulatory agencies and the Lower Manhattan Construction Command Center (LMCCC), while ensuring public notice and outreach on all significant activities.

Frequently Asked Questions

For a full list a frequently asked questions about Fiterman Hall, please click here.


Daily Activities

*The following information was last updated on September 11, 2007.

The standpipes for Fiterman Hall were re-tested by the Fire Department on August 22, 2007, and were found to be operational.

New scaffolding is now being erected around the building and is expected to be complete by early September 2007, including installation of new netting.

The scaffolding work and netting replacement follows the plan's approval by the city Department of Buildings and federal Environmental Protection Agency, as well as several weeks of air sampling to serve as background data during the deconstruction.

EPA approval to being decontamination work is also expected in August 2007. Decontamination and deconstruction are expected to take four to six months each after the EPA approves the plan.

The FDNY is inspecting the building for proper fire and emergency equipment.

Project History

From 2002 though 2004 CUNY and DASNY negotiated insurance claims on Fiterman Hall. After sufficient funding was in place to determine the scopeof the project, the project team selected the architectural firm of Pei Cobb Freed & Partners to both lead the development of the building’s hazardous waste cleanup and demolition procedures as well as design the new building. Pei Cobb continues to work with a team of design, construction, and environmental professionals. Tishman/Liro, a construction management firm, is also providing services for the deconstruction and decontamination work.

During the summer and fall of 2005, the Fiterman project proceeded along two tracks: planning for the decontamination and deconstruction of the original building (Phase 1) and designing the new building that will replace it (Phase 2). The architects working on design documents for Phase 2 are operating under the assumption that the new building will be approximately the same size as the old building. The new facility will provide space for classrooms, computer labs, offices, assembly and meeting rooms, and other spaces to accommodate college programs and community functions.

DASNY advertised for a general contractor for Phase 1 with a December 29, 2005, deadline for Expressions of Interest and Statements of Qualifications. Bids from the pre-qualified contractors were due on May 9, 2006. The contractor selected in the bidding process would be responsible for interior and exterior environmental cleaning, including building contents, erecting the scaffold, and deconstruction. All work would be conducted under special monitoring requirements applicable to the United States Environmental Protection Agency (USEPA) WTC Recovery Zone and will occur within the jurisdiction of the USEPA WTC Recovery Program. The entire structure will be sealed and scaffolded during the remediation process.

On May 9, 2006, DASNY opened contractor bids for remediation and demolition. After reviewing all four bids, in July 2006 the Authority determined that none were fully responsive to all environmental specifications and decided to re-bid the project. An addendum to clarify requirements and expectations was prepared for the pre-qualified firms. From the pool of pre-qualified contractors, DASNY sought a new round of bids due on August 3, 2006. PAL Environmental Safety Corp., 11-02 Queens Plaza South, Long Island City, was selected for Phase 1. The contract value is $16,313,000.

To start construction as soon as possible, DASNY advertised in the New York State Contract Reporter for a construction manager (CM) for the new building. Expressions of Interest were received on January 12, 2006. The CM will hold all construction trade contracts for the project in a CM-at-Risk or CM-Build capacity.   Firms were required to demonstrate successful completion of similarly complex projects in the New York City region. In the summer of 2006, Hunter Roberts Construction Group was selected as the CM to over see the construction of the new Fiterman Hall.

Environmental Issues
Remediation and Regulatory Reviews

Development of the decontamination and deconstruction plan began in June 2005. The project team consulted with federal, state, and local environmental, health, and regulatory agencies to develop a safe and efficient plan. By the fall of 2005, a draft decontamination outline was ready for CUNY and DASNY review. Site access and traffic plans were coordinated with the Lower Manhattan Construction Command Center (LMCCC). Consultants continued to study contaminants in the building, as well as construction safety issues. The required State Environmental Quality Review (SEQR) is also being conducted in tandem with development of decontamination and deconstruction plans.

In January 2006, the project team submitted the preliminary decontamination and deconstruction plan to the EPA for approval, with comments from EPA received on April 14, 2006. On October 5, 2006, the project team submitted the scaffolding plan, as a submission separate from remediation and deconstruction plans, to the EPA. This submission also included the Environmental Characterization Report, Facade Characterization Report, and Environmental Community Air Monitoring Plan. Comments on this submission were received from the EPA on December 13, 2006.

On March 23, 2007, the EPA approved Fiterman Hall Scaffold Plans. Airtek Environmental Corp., the environmental consultant for the project, has installed air monitors and started the required two-week background sampling period. After sampling results from this period have been reviewed by the EPA, work to install the scaffold is anticipated to commence in mid-April.

In December 2006, revised draft submittals for the clean-up phase of the Remediation Phase were made available for public comment on the BMCC Fiterman Hall News and LowerManhattan.info websites. After the public comment period, the revised full remediation plan was submitted to the EPA on January 17, 2007. Once the remediation plans are approved and work commences, the remediation and deconstruction work should be complete within 10 to 12 months. Deconstruction will commence after the building is fully cleaned and abated.

The project team has also drafted an Emergency Action Plan and Community Notification plan to address the unlikely event that the remediation or deconstruction work causes unsafe conditions. This draft plan has been made available to the community and was sent to the New York City Office of Emergency Management and the police and fire departments for review. When comments from concerned parties have been received and incorporated into the document, the project team will re-issue the plan.

On Friday, March 23, 2007, the EPA approved Fiterman Hall Scaffold Plans. Airtek Environmental Corp., the environmental consultant for the project, has installed air monitors and started the required two-week background sampling period. After sampling results from this period have been reviewed by the EPA, we anticipate the work to install the scaffold will commence in mid-April.

Community Outreach Efforts

The project team is committed to the safe and efficient decontamination, deconstruction and rebuilding of Fiterman Hall. The team continues to work closely with regulatory agencies and the Lower Manhattan Construction Command Center (LMCCC) to ensure timely public notice and outreach on all significant activities.

Since June 2005, there have been regular updates both to the World Trade Center Redevelopment Committee of Community Board 1 and at the bi-weekly Community Outreach Meetings of the Lower Manhattan Construction Command Center. NYS Assembly Speaker Sheldon Silver hosted well-attended meetings on September 7, 2006, and October 25, 2006, at which CUNY and DASNY provided project updates to a wide spectrum of legislators, representatives of elected officials, community, business and labor leaders. A public information session co-sponsored by Community Board 1 was held on October 30, 2006, at BMCC, with representatives from DASNY, CUNY, the environmental consultant, the construction management firm, and the contractor providing updates and answering questions. A follow-up meeting is scheduled for January 30, 2007, at 6:30 p.m. at the BMCC campus,   and regular update meetings are planned for approximately every six weeks.

In November 2006, BMCC with CUNY launched a new e-mail newsletter, “Fiterman News: Keeping Our Community Informed.” More newsletter updates will follow as the project progresses. BMCC has also created a comprehensive website, www.bmcc.cuny.edu/fitermannews. This site will host the e-newsletter and anchor news about Fiterman. The site hosts a special subscription link to regular e-mail delivery of Fiterman News updates. Visitors can view architectural slideshows of the new Fiterman Hall. The site will also have a “Questions and Answers” feature which will enable visitors to email questions and obtain responses from college administrators.

In addition, at the request of public officials, CUNY has set up a Community Advisory panel consisting of federal and state legislators, local officials, college and university representatives, Community Board 1 representatives, and LMCCC representatives, as well as other community organizations, concerned citizens and other stakeholders. The first meeting of this committee will be held in NYS Assembly Speaker Sheldon Silver’s office on February 9, 2007, at 10 a.m.

As the project moves forward, BMCC, CUNY, and DASNY have enhanced outreach to ensure that all stakeholders receive news and information as soon as it becomes available and to provide an interactive space for community questions and concerns. The latest, up-to-date information on the project can be found here on this page, so please check back often.


Contact Info

  • Max Pizer
    Assistant Director
    Department of Design, Construction, and Management
    City University of New York
    555 W. 57th St., New York, NY 10019
  • Paul J. Burgdorf
    Dormitory Authority of the State of New York
    515 Broadway, Albany, NY 12207 

Fiterman Hall Air Monitoring Results

Regulatory Submittal Documents

Other Related Documents

Archived Submittal Documents


Frequently Asked Questions

Click here for answers to commonly asked construction questions.

Related Links

Fiterman Hall News -- A Website from the BMCC on Building Plans and Progress
Locate this project on the Interactive Streetwork Map
Fiterman Hall Air Monitoring Results
Special Feature
> Construction Lingo
> Construction Questions Answered
> Q&A With Charles Maikish
> Support the Memorial
> Envisioning the Future
Headline
- Plans Announced for Sixth Anniversary of 9/11
- New Website Consolidates 9/11 Health-Related Info
- Community Alerts Top Priority List at 130 Liberty
- State Program Improves MWBEs Access to Contracts
- Update On Fire at 80 Washington Street
- New Library Headed to Battery Park City
- 130 Liberty Air Monitoring Test Results
Community Happenings
This is Lower Manhattan
   
> View Video > Looking Ahead

Current Construction | Programs in Lower Manhattan | Get It Fast Latest Advisories | News and Image Gallery | About the LMCCC
Home | Search | Fraud Prevention | Get Email Updates | Related Links | Media Center | Information Library | Contact Us | About the Site

© 2007 Lower Manhattan Construction Command Center/LMDC

RSS Feed - Really Simple Syndication RSS Feed