KUDANKULAM ATOMIC POWER PROJECT 1 & 2    
 
 

AUDITED FINANCIAL RESULTS FOR THE YEAR ENDED 31ST MARCH, 2007
[ENGLISH] [HINDI] [MARATHI]


 
Last Updated : May, 2008
Location Kudankulam, District : Tirunellveli-Kattabomman, Tamil Nadu State.
Reactor type V V E R -1000 (PWR)
Capacity 2 x1000 MWe
Scheduled Date of Commercial Operation Unit-1 : Dec '07
Unit-2 : Dec '08
Expected Date of Commercial Operation Unit-1 : Jun '09
Unit-2 : Mar '10
Physical progress achieved Kudankulam - 1 : 85 % as on Apr. , 2008
Kudankulam - 2 : 75.4 % as on Apr. , 2008
Kudankulam - 1 & 2 : 81.2 % as on Apr. , 2008
Major Milestones Achieved 
 
Activity Unit - 1 Unit - 2
Construction of Inner Containment (IC) Dome Oct - 2007 -
Construction of Primary Containment Wall upto 43.9M May - 2005 -
Construction upto + 5.4 Slab Sept-2003 Dec-2003
Completion of 0.00m Slab March - 2003 June-2003
Completion of Foundation Slab July - 2002 Sept. - 2002
First Pour of Concrete March-2002 July - 2002
Ground Break Sept-2001 Sept-2001
 
   