Status of Construction Activity

Recently Completed Projects

Location

Length

Completed

Musquash River to MacTier

8 km

Summer 2008

Estaire Bypass

6.5  km

November 2008 (to be opened with Estaire to Highway 537 paving contract)

Estaire to Highway 537

4.1  km

April 2009 (to be opened with Estaire to Highway 537 paving contract)

Interchange at Gladu Road

2.4 km

June 2006 (to be opened with Highway 537 to Sudbury)

Old Wanup Road underpass

0.6 km

July 2006 (to be opened with Highway 537 to Sudbury)

 

Projects Currently Under Construction

Location

Length

Planned Completion

Parry Sound to Nobel. Construction started June 2005

7 km

2011

Nobel Bypass.  Construction started October 2006

5 km

2011

Nobel to Highway 559. Construction started January 2008

5 km

2011

Highway 537 to Sudbury. Construction started January 2005

8.6 km

Fall 2009

Murdock River to Highway 637. Construction started April 2008.

4 km

2010 (two lanes)

Estaire to Highway 537 Paving

11 km

Fall 2009

 

Projects Currently In Planning / Engineering / Property Acquisition

Location

Length

From Highway 559 to Highway 7182 (Shebeshekong Road)

16 km

From Highway 7182 (Shebeshekong Road) to the South Junction Highway 529

11 km

From the South Junction Highway 529 to Harris Lake Road

14 km

From Harris Lake Road to Highway 522

27 km

Highway 522 to Highway 64

25 km

Highway 64 to Estaire

22 km