History of the Plant

 Stages of development

Number of unit, type of reactor

1
WWER-210

2
WWER-365

3
WWER-440

4
WWER-440

5
WWER-1000

Start of construction 

1958

1964

1967

1967

1972

Commissioning 

Sept
1964

Dec
1969

Dec
1971

Dec
1972

May
1980

Full capacity operation

Dec
1964

Apr
1970

June
1972

May
1973

Feb
1981

Decommissioning

1984

1990

2001

Project service life

2002
P.s.l.

2010
P.s.l.