Brief Introduction to

the Three Gorges Project Construction

 

By China Yangtze Three Gorges Project Development Corporation (CTGPC)

 

Three Gorges Project is the largest water conservancy project ever built in the world. The dam site is situated in Sandouping of Yichang City, Hubei Province, about 38km upstream from the existing Gezhouba Project. The project is composed of a dam, two powerhouses and navigation facilities. The spillway section is placed in the center, while the powerhouses are arranged on its both sides. The permanent navigation structures are located on the left bank side. The dam is of a concrete gravity type. The total length of the dam axis is about 2,309 meters, with the crest elevation at 185m. There are 14 sets of hydro turbine generator units installed in the left powerhouse while 12sets in the right. Thus, there are 26 sets of turbine generator units in total, 70OMW for each, totaling 18,200MW in installed capacity that will produce 84.7TW h of electricity output annually. The dynamic cost of TGP is 203.90 billion RMB Yuan by rough estimate. The total duration of construction will last 17 years, divided into three stages. The first stage construction lasts 5 years from 1993 to 1997. The second stage construction lasts 6 years from 1998 to 2003. The third stage construction lasts 6 years from 2003 to 2009. After the project completed, the total storage capacity of the reservoir will be 39.3 billion m', with the normal pool level at 175m. It will be the most important project functioning as a backbone in flood control system to protect the areas in the middle and lower reaches of Yangtze River With a 22.15 billion m' of flood control storage capacity of the reservoir, the Jingjiang River Section will be able to raise its flood control capability from the present 10-year frequency to the 100-year. And the 660km long waterway from Yichang to Chongqing will obviously be improved, making it possible for 10,000 tons of barge fleet to sail upstream directly to Chongqing.

 

 

wpeD.jpg (3781 bytes)Exhibition Hall of Three Gorges

China Yangtze Three Gorges Project Development Corporation (CTGPC) is an autonomous economy entity, keeping separate accounting, assuming sole responsibility for its profits and loses, with legal entity position, and is the owner of the project, responsible for the overall construction of the project and its management of operation and maintenance after the completion of the project, and also responsible for the financing and reimbursement of investment including the fund for resettlement Gezhouba Power Plant is a component part of CTGPC. The corporation is sincerely looking forward to cooperating with all interested organizations and individuals from all over the world.

Dam Area The total construction area of dam site is 15.28 km. Its fundamental establishment and enclosed management provide favorable conditions for TGP construction. The dam area is planned to be a National forest Park, and will turn to be a worldwide famous tourism scenic spot, where actual scenery and modern project are combined together.

 

Second Stage Construction On Nov. 8, 1997, the closure of Yangtze River¨s grand channel has been achieved successfully. From then on, the second stage construction has begun. The main objectives of the construction are as follows: Concrete pouring of the spillway section, left powerhouse section and none overflow section will begin and reach the elevation of 1854m; concrete placement is going on the upstream head of the shiplift, and the permanent ship locks will be put into operation; The 2nd stage up-and down-stream cofferdams will be removed and the impounding water of the reservoir will begin and reach the pool level of 135 m, In Dec. 2002, the diversion channel will be enclosed and the upstream 3rd stage RCC cofferdam is to be built in it before flood season. According to the scheme, 17 million m of concrete will be poured, 180,000 tons metal structures will be installed, and 80 billion RMB Yuan will be invested during the 2nd stage construction.

wpe14.jpg (4492 bytes)Landscape of Xiling Yangtze Bridge

Second Stage Transverse Cofferdams were built on both upstream and downstream so as to form, together with the completed RCC longitudinal cofferdam, the 2nd stage construction pit. The total length of the upstream cofferdam axis is about 1,400 m, with crest elevation at 88.5m. While the length of the downstream cofferdam axis is about 1,075m, with crest elevation at 81.5m. Concrete was poured inside the cofferdams so as to prevent water from infiltrating.

Spillway Section and Left Powerhouse Section concrete placement of the spillway section and left powerhouse is the main construction work in 1999. 3.42 million-m concrete is designed to be poured, and metal structures will be installed. Till the end of this year, left powerhouse section will be 30m higher. In 2003, the first batch of generation units will be put into operation.

 

wpeE.jpg (5344 bytes)Exhibition Hall

Permanent Shiplock is situated on the left bank. The main work quantities of the shiplock consist of earth-rock excavation of 36.85 million m, concrete pouring of 3.57 million m, metal works erection of 41,700 tons. The shiplock is 1,607m long, schemed as a double-lane and five-step flight locks, each lock chamber is dimensioned at 280x34x5m (length width minimum water depth) capable of passing 10,000 tons of barge fleet. The total length of underground water feed and empty system is about 7,000m. It takes over 2 and half hours for ships going through the permanent shiplock. By the end of this year, all the excavation work for the lock chambers will be finished. Metal structures installation of lock gates will start in 2000, complete in June, 2003. According to the scheme, the permanent shiplock will be put into operation in July, 2003.

Temporary Shiplock was in use on May 1, 1998. It is the main navigation facility during the 2nd stage construction, especially in flood season. The effective chamber size is 240x24x4m (length x width x minimum water depth).

Shiplift works like an elevator. It is designed as a one stage vertical hoisting type wit ha ship container sized 120 x 18 x 3.5m (length x width x minimum water depth), capable of carrying one 3,000 tons passenger or cargo boats each time. The capacity of annual one-was navigation is 3.5 million tons. It only takes 40 minutes for boats going through. It is schemed to be put into operation by 2009.

wpeF.jpg (5866 bytes)Exhibition Hall

Equipment for concrete placements Of all the equipment used in the 2nd stage concrete placements, 18 units are made in overseas while 12 ones are domestics. Seven concrete mixing plants at different elevation can convey different kinds of concrete to 6 tower-belt conveyer system, 4 mobile belt conveyers, 8 gantry cranes, 1 tower crane, 2 cable cranes, 2 caterpillar cranes receptively. Among those, ROTEC tower-belt conveyer system made in the United States is advanced and newly in structure. It is composed of tower crane and belt-conveyer the conveying system can rotate with a radius of 80m to fulfill the need of massive concrete works, extremely in high intensity.

wpe2.jpg (5067 bytes)Temporary shiplock

The Artificial aggregate systems can crush different size of granite into aggregate. The aggregate systems in TGP dam site are located at Gushuling and Xia¨anxi. The aggregate system in Gushuling and Xia¨anxi. The aggregate system in Gushuling is situated between the permanent ship-lock and the temporary shiplock on the left bank, with a coarse production capacity of 482600 m monthly. While Xia¨anxi aggregate system, the biggest one in the world, is sited at Jigongling beside TGP Expressway, with a fine size aggregate production capacity of 261000 m monthly.

Tanziling is the top point in TGP dam site at elevation 262.48 m, around which is dressed up with embossments about mankind and water. On Tanziling, you can have a bird¨s-eye view of the 15.28 km TGP dam area. After the completion of TGP Tanziling will be a permanent sightseeing point.

TGP Expressway With the length of 28.60 km, TGP Expressway, which began to be built in 1994, and was opened in October 1996, cost 1 billion RMB Yuan. Along the Expressway there are 34 bridges with 4 special long ones and 5double-line tunnels with a 3610m-long Muyucao tunnel in single line which is the longest one in China¨s highway tunnels. Being called the museum of bridges and tunnels, the Expressway, with bridges and tunnels come to 40%, is the stem road in the communication of TGP.

 

wpe10.jpg (5813 bytes)Exhibition Hall

Xiling Yangtze Bridge, located 4.5 km downstream from TGP dam site, is the main road between the left and the right banks. It was opened on August 10th, 1996. The bridge is suspension type with the length of 1118.66m and the load capacity of 290 tons. The single span of this bridge is 900m, and the crest elevation of the tower is 187.5m. The width of the bridge is 18m with 4 lanes and two sidewalks on its both side. The diameter of the two tight wires is 57 cm, and the tight wire is composed of 10010 pieces of steel wire. The bridge is like a rainbow goes through the north and south banks of the Yangtze River.

wpe6.jpg (6297 bytes) Training Center

The Three Gorges Dam Area Reception Center invested by CTGPC, is a modern hotel built standardized after international star hotel. The 26-floor building accommodates 506 guestrooms including standard rooms, single rooms, executive suites, deluxe suites and presidential suite. Each of the guestrooms is equipped with central controlled air-condition, IDD system, mini-bar, refrigerator, cable TV to make your stay enjoyable. The hotel has a Chinese restaurant, providing you with Sichuan and Guangdong dishes, Western restaurant gives you a good taste of European cuisine, and "century" dining hall is an integration of Chinese and western style. Bar provides you with a n elegant environment and relaxing atmosphere. There are also Business Center, Shopping Arcade, Bowling Rooms, Fitness Room, Billiard Room, Beauty Salon, Dancing Hall, and Meeting Rooms and so on in the hotel.

The Training Center is a foundation for training and education of CTGPC; it has apartment building, educating building and dining hall. Advanced acoustics, lamplight and multimedia computer system has been equipped in the education building. There are modern equipment and 6-way language simultaneous interpretation in the 260-people international meeting hall. There are 7 classrooms in different sizes, 30-seat computer classroom and a compute assistant design room, all of which can hold 560 people.

wpe71.jpg (11815 bytes)

The Three Gorges Exhibition Hall was opened on October 1st, 1992, with a proportion of 6600 m. According to special topics, the Exhibition Hall can be divided into TGP construction, environment protection, resettlement, scientific and technological development, power generation, painting and calligraphy, photography and so on. The Exhibition Hall is arranged standardized after international exhibition, with film hall and honored guest hall in it. There is a color-sprayed three gorges hold landscape in the lobby, which is the biggest one in China with grandiose momentum.

wpe11.jpg (5385 bytes)Exhibition Hall

 

Relating topics:

Three Gorges Project, Water Level and Scenic Spots Affected

Three Gorges Dam Scheduled to Block Up in November 2002

Three Gorges Project (TGP)

Why China Builds the Big Dam

Report on Environmental Impact of the TGP

Gezhouba Dam

Some facts about the Gezhouban Dam

Three Travelers' Cave

Nanjin Pass

Yichang

  


Home | Yangtze gallery | News & promotions  | Cruise ships | Cruise schedules |

Tours | Services | FAQ | Resources | Travel agent | Testimonials | About us

 

(Yangtze Logo)
566 7th Ave, Suite 805
New York, NY 10018

Contact your local travel agent, or call:
Reservations: (800) 779-2856

Telephone: (212) 382-3725
Fax: (212) 382-3701

E-mail: info@YangtzeCruises.com
www.YangtzeCruises.com

 

CLIA LOGO

For more information or comment, please contact Yangtze Cruises, Inc. Tel: (800) 779-2856 (US & Canada), (212)382-3725 Fax: (212) 382-3701. Email: info@YangtzeCruises.com.

Copyright ©   Yangtze Cruises, Inc. 1995-2003. All rights reserved.