For many years the Met Office has verified its forecasts by comparing
actual with forecast sea-level pressures and calculating a forecast
error. The graph shows how many days into a forecast period this
error is reached compared to a baseline in 1980. This graph shows
that a three-day forecast today is more accurate than a one-day
forecast in 1980.
These comparisons are based upon the 36-month root-mean-square errors
of mean sea-level pressure forecasts over an area covering the North
Atlantic, most of western Europe and north-eastern parts of North
America. This area was chosen because of the long history of verification
statistics going back many years to before the time the Met Office
ran a global NWP model.

|