-
The structure will form a cross in the traditional manner of
European cathedrals
-
The new Co-Cathedral will seat 1,820 people with space for 200
additional chairs
There are about 8,000 cubic yards of concrete in the cathedral:
-
That is a little more than three football fields
-
That's enough to pour a four-foot wide sidewalk from the
cathedral to The Woodlands (going north) or to League City
(going south)
-
The weight of 8,000 cubic yards of concrete is
32,400,000 pounds
There are about 250 tons of steel in the cathedral
-
That is almost half a million pounds
-
The dome weighs about 80,000 lbs. It will be
constructed on the ground and lifted into place, where it will
stand 117 feet tall
There are about 73,000 square feet of Indiana limestone on the
exterior of the cathedral
-
That is a little less than two football fields or a
sidewalk three and a half miles long
-
The weight of the exterior stone is 2,633,000 pounds
-
The exterior nave will be 86 feet wide
-
The interior nave will be 72 feet tall
There are about 30,000 square feet of marble on the interior of the
cathedral
-
That's a little more than half of a football field or a
sidewalk one and a half miles long
-
The weight of the interior stone is approximately
300,000 pounds
There are about 86,000 square feet of plaster on the cathedral walls
and ceilings
-
That is almost two football fields or a sidewalk almost
4 miles long
-
The weight of the plaster is about 1,290,000 pounds
There are 256,500 linear feet of wire in the cathedral
-
Stretched end-to-end that would be 48 miles long
*Total weight of these items in lbs:
37,123,000
*Total weight of these items in tons: 18,562
*Does not include weight of roofing
materials, windows, reinforcing steel, cabinets or other furnishings
or fixtures
-
There are two 160 ton chillers to air condition the
cathedral
-
There are 14 air handlers to distribute air around the
building
|
Size: |
|
Total Area: |
Footprint
27,800 s.f. |
|
Building Area
37,000 s.f. |
Seats: |
Cathedral
1,820 (with room for 200
temporary chairs) |
Height: |
Dome
117 ft |
|
Campanile
140 ft |
|
Interior Nave
72 ft |
Cathedral Spaces: |
Main Worship Space |
|
Choir Loft |
|
Campanile |
Support Spaces: |
Narthex |
|
Cry Room |
|
Sacristies |
|
Restrooms |
|
Elevator |
|
Organ room |
Site: |
Middle of three
blocks owned by the Archdiocese of Galveston-Houston in Downtown
Houston. Site is bound by St. Joseph's Parkway, Fannin, Jefferson, and San Jacinto. |
Building
Materials: |
Walls
clad in limestone and marble |
|
Metal dome roof |
|
Stained glass |
|
Glass & metal detailing |
|
Natural wood accent panels |
Ziegler Cooper Architects |
|
Linbeck Construction Corporation |
|
-
Substantial
completion
September 2007
-
Site
complete
August 2007
-
Interior stone
complete
July 2007
-
Interior plaster
complete
May 2007
-
Exterior stone
complete
November 2006
-
Interior plaster
begins
April 2006
-
Exterior stone
begins
April 2006
-
Structural steel "topped out" / dome
raised March 31, 2006
-
Concrete structure
completed
March 3, 2006
-
Interior stone
begins
January 2006
-
Construction started / first pier
drilled May 16,
2005
-
Linbeck released to proceed
w/construction March 2005
-
Groundbreaking and site blessed by
Archdiocese January 30, 2005
-
Linbeck engaged for preconstruction
services February 26,
2001
-
Linbeck presentation to building
committee January 18, 2001
-
Linbeck received RFP from
archdiocese
December 6, 2000
|