COMPLETED
PROJECTS |
2004 |
October 2004 |
Roads, Grounds and Security - Initiated as a direct result of the terrorist attack, the Pentagon Roads, Grounds, and Security projects will enhance Pentagon perimeter security. With a combined total value of $35 million, these initiatives will increase standoff distance between the Pentagon and public roadways. |
|
Rendering of Route 110 Secure Bypass. |
|
March 2004 |
The Pentagon Athletic Center (PAC) -The Pentagon Athletic Center (PAC) will replace the existing 55-year old Pentagon Athletic Facility with a larger, modern facility that meets membership fitness and readiness needs based on current usage patterns and anticipated incremental growth. The 130,000-square-foot facility will be located at basement level underneath and adjacent to the Pentagon's Mall Terrace. |
|
Rendering of the new lap pool and running track. |
|
2003 |
June 2003 |
Navy Build-out 2A1 - Navy requires approximately 25,000 square feet of space in the Pentagon. The area designated for this project in Basement Segment 2A1 is the only available space. |
|
Early basement renovation in Segment 1. |
|
2002 |
November 2002 |
Metro
Entrance Facility (MEF)
-
The
Metro Entrance Facility project was directed by Congress in
the FY2000 Department of Defense Appropriations Act in response
to recent
security assessments that identified the need to improve the
physical security of the Pentagon. These initiatives involve
relocating the current bus station and removing the existing
direct entry into the Pentagon from the Metrorail station. |
|
Currently,
buses and other vehicles pass within feet of the Pentagon necessitating
the relocation
of the Pentagon bus facility. |
|
September 2002 |
Phoenix
- The
Phoenix Project is rebuilding the section of the Pentagon that
was most severely damaged in the September 11 disaster. The
area of work extends from Corridor 4 to Corridor 5, C, D and
E Rings and represents roughly 400,000 square feet of the Pentagon.
Half of this area rests in Wedge 1 of the Pentagon and the other
half of the area rests in Wedge 2 of the Pentagon. The Phoenix
Project scope of work includes rebuilding the core and shell
of Wedge 1 and only the Shell of Wedge 2.
|
|
An
aerial photo of the Pentagon taken on September 14, 2001
three days after the terrorist attack.
|
|
2001 |
December 2001 |
Metro Entrance
Facility (MEF) - Phase I |
September 2001 |
Wedge
1
-
The renovation
of the five floors in Wedge 1, approximately 1 million square
feet of space, began in 1998. The project included major structural
demolition, installation of new utilities, and the build-out
of tenant areas. A phased move-in of tenants began in February
2001. Wedge 1 is accessed by Corridors 3 and 4. |
|
Wedge
1 officially opened with a ribbon-cutting ceremony on March
8, 2001. |
|
February 2001 |
South Terrace
Pedestrian Bridges |
January 2001 |
Heliport Fire Station and Control Tower |
2000 |
December 2000 |
Remote
Delivery Facility (RDF) -
The Remote Delivery
Facility (RDF) is a new 250,000-square foot shipping and receiving
facility adjoining the Pentagon. The RDF significantly improves
the physical security of the Pentagon by providing a secure
consolidated location for receiving and screening thousands
of items shipped to the building each day. |
|
An
aerial photo, taken January 4, 2001, shows the RDF nearing completion.
The loading docks
opened on August 31, 2000. |
|
October 2000 |
Basement Segment 3A Demolition and Abatement |
September 2000 |
Replacement of Underground Water Line |
August 2000 |
Remote Delivery Facility Phase 1 |
March 2000 |
DiLorenzo TRICARE Health Clinic |
March 2000 |
Basement/Mezzanine
- Basement
and Mezzanine levels exist under three fifths of the Pentagon.
This area has been divided into three segments. Segment 1 has
been renovated and is now occupied by 1,200 Air Force personnel
and the new DiLorenzo TRICARE Health Clinic. Segments 2 and
3 have been demolished and abated of all hazardous materials. |
|
The
basement floor slab was excavated and lowered two feet. This
allowed enough room to build and entirely new mezzanine level,
an addition of 240,000 square feet of space. |
|
1999 |
October 1999 |
Basement Segment 2A2 |
September 1999 |
Mug Handle Infill |
June 1999 |
Renovation and Furnishing of Swing Space Facilities |
1998 |
August 1998 |
River Terrace Renovation |
May 1998 |
Corridor 8 Entrance Renovation |
1997 |
October 1997 |
River Terrace Vehicle Bridge |
September 1997 |
Heating and Refrigeration Plant |
August 1997 |
Classified Waste Incinerator |
June 1997 |
Center Courtyard Utility Distribution Tunnel |
February 1997 |
Sewage Lift Station |
January 1997 |
River Terrace Handicapped Access Lift |
1996 |
November 1996 |
North Parking Pedestrian Ramp |