Western three miles of the line from anticipated start to substantially complete

  • Hiawatha LRT tie-in (at map’s left edge) to Pleasant Street (just east of the Mississippi River before the East Bank Station) — Jan. 2011 to Nov. 2012
  • West Bank and Washington Avenue Bridge — Sept. 2010 to Nov. 2012
  • Transit mall (from Pleasant to Walnut streets encompassing the East Bank Station) — May 2011 to Aug. 2012
  • Oak Street (just east of the transit mall) — May 2011 to Nov. 2011
  • Oak to Emerald Street (border between Minneapolis and St. Paul) — March 2012 to Nov. 2012
  • Transitway reconstruction (between the Stadium Village and 29th Avenue stations) — May 2011 to Aug. 2011

 

Eastern seven miles of the line from anticipated start to roadway substantially complete

  • University Avenue from Emerald to Hamline Avenue — March 2011 to Nov. 2011
  • University from Hamline to Robert Street (where Capitol East Station is located) — March 2012 to Nov. 2012
  • Robert to 12th Street (where tracks turn southwest for a short distance before turning southeast to cross Interstate 94), 12th to Cedar Street — Aug. 2010 to Nov. 2010
  • Cedar Street — June 2011 to Nov. 2012
  • Bremer Bank (at northwest end of Fourth & Cedar Station) — April 2011 to Nov. 2011
  • Fourth Street — Aug. 2009 to Nov. 2010

 

 