Airport Improvement Projects
The grand finale…
The terminal expansion project started June 2009 and was completed December 2010. As you may know, Jackson Hole Airport is the largest airport in Wyoming and employs over 500 full time workers with an economic impact of over $500 million for Wyoming. This key gateway project includes 52,000 square feet of new, and 48,000 square feet of renovation.
Terminal Expansion Project Projected Milestones
May 10, 2010 CBIS and BHS Testing Completion/Certification
May 26, 2010 Grand Opening of new Ticketing Hall
July 26, 2010 Completion of Phase 2 and Opening of new gate area and restaurant
Sept. 27, 2010 Completion of Phase 2A Open remodeled existing gate area.
Sept. 27, 2010 Entire boarding area complete.
Dec. 14, 2010 Completion of remaining Phases 2B (checkpoint) and 3 (inbound baggage area remodel)
Dec. 14, 2010 Project Completion.