ANA to get first 787 in late July, JAL, Air India and China Southern to follow in 2011

| | Comments () | TrackBacks (0) |
ANA 787-8 JA804A

SCOTTSDALE -- With the latest iteration of its 787 schedule, Boeing aims to hand over the first aircraft to Japan's All Nippon Airways in late July, the first of 20 planned for delivery in 2011, according to several sources familiar with the new plan.

While Boeing won't confirm the late July guidance, that target remains in line with an "early summer" completion of flight test activities.

Industry officials said previously the carrier had been provided a September guidance by Boeing for its first delivery following the November 2010 fire that prompted an additional six-month delay in first delivery, though the latest schedule reflects a more optimistic target for first delivery.

Boeing's official guidance reflects a third quarter target, allowing the company to deliver the first 787 anywhere from July 1 to September 30.

Several sources familiar with Z23, the latest 787 delivery plan, say Airplane Eight - also known as ZA101 - the second production 787, will be the first 787 to be delivered and will feature a two-class medium to short-haul configuration for the Japanese carrier.

ANA will receive its first long-range configured 787, Airplane 24, in August, which will sport an increased maximum takeoff weight (MTOW) of 502,500lbs (227,930kg) for recovered payload range performance. All aircraft after line number 20 have the MTOW.

Airplane Seven, which was initially expected to be the first 787 delivered, along with Airplane Nine, which is now sequestered for delivery preparation, and Airplane 31 will be handed over to the carrier in September, with Japan Airlines' first - Airplane 23 - to follow in October.

At the opening of its 787 change incorporation facility in San Antonio, Texas - which now hosts Airplane 23 - 787 program vice president and general manager, Scott Fancher says Z23 may not be the final plan, saying the delivery "sequence is still evolving a bit, and that is still somewhat coupled to our detailed plans on F&R (functionality and reliability) and ETOPS (extended operations), and once we settle that out and settle in on a delivery sequence." 

Fancher adds "we are absolutely focused on getting through F&R and ETOPS before delivery", which is expected to get underway in the "next couple of months". 

Nineteen aircraft will follow after the July first delivery in 2011 and ANA will be joined by Japan Airlines, Air India and China Southern.

Photo Credit Angad84

0 TrackBacks

Listed below are links to blogs that reference this entry: ANA to get first 787 in late July, JAL, Air India and China Southern to follow in 2011.

TrackBack URL for this entry: http://www.flightglobal.com/cgi-bin/mt/mt-tb.cgi/196113

Cookies & Privacy