SHATIN TO CENTRAL LINK – NORTH SOUTH LINE
Prequalification for Electrical and Mechanical Contract
Expressions of Interest are invited from contractors who wish to submit a tender for
New Rolling Stock for SCL Phase 2 (NSL)
(Contract No.: 1141B)
1.
|
Background Information
|
|
The Shatin to Central Link (SCL), which consists of the North South Line (NSL) and the East West Line (EWL), is a strategic railway line that runs through multiple districts in Hong Kong to strengthen the current railway networks by connecting several existing lines through a number of interchange stations. The NSL is a 6-km extension of the East Rail Line from Hung Hom Station across the harbour to Admiralty Station, forming the North-South rail corridor. The 11-km EWL extends the Ma On Shan Line from Tai Wai Station to Hung Hom where it will connect to the West Rail Line to form an East-West rail corridor.
To serve the NSL, new trains will be procured.
The East Rail Line trains are Electric-Multiple-Units operated by 25 kV ac traction supply. The maximum service speed is 120kph. Train operation is currently under ATO/ATP signaling control and the new train will be capable to operate in Fully-Automatic-Operation.
|
2.
|
Scope of Works
|
|
The scope of works comprises the design, manufacture, supply, delivery, installation, testing, commissioning and rectification of defects during the defects liability period for the new trains, including the provision of special tools and testing equipment, spare parts, operation and maintenance manuals, training, etc. to facilitate the operation and maintenance of the trains.
|
3.
|
Key Dates (All tentative)
|
|
Contract
|
Tender Issue
|
Tender Return
|
Contract Award
|
Contract Completion
|
1141B
|
Q1/2012
|
Q2/2012
|
Q3/2012
|
2020
|
|
4.
|
Expressions of Interest
|
|
In order to be considered for prequalification, interested parties having relevant resources, qualifications and experiences are requested to express their interest on or before 14:00 (Hong Kong Time) on 7 October 2011 via the MTR Corporation Limited's E-Tendering System. Late applications will not be considered.
For contractors registered under the E-Tendering System, please click the following link and log into the system for expression of interest: http://www.hkextender.com
For contractors not registered under the E-Tendering System, please click the following link and search for the advertisement notice of Contract 1141B for registration and expression of interest: http://www.hkextender.com/process/GuestLogon.asp
|
5.
|
Closing Date for Return of Answers / Information
|
|
Upon expression of interest, the contractors will receive invitation of prequalification via the E-Tendering System within 2 weeks of 7 October 2011. The contractors shall complete and submit all information and details as required in the invitation via the E-Tendering System no later than the time specified in the prequalification invitation letter.
All invitations and submissions for prequalification and tender will be carried out through the E-Tendering System at http://www.hkextender.com.
For enquiries, please contact Mr Jason Lau, Senior Contracts Engineer, via jwslau@mtr.com.hk.
|