Funding

USEC needs significant additional financing in order to complete the American Centrifuge Plant. USEC believes a loan guarantee under the DOE Loan Guarantee Program, which was established by the Energy Policy Act of 2005, is essential to obtaining the funding needed to complete the ACP. In July 2008, USEC applied under the DOE Loan Guarantee Program for $2 billion in U.S. government guaranteed debt financing for the ACP. Instead of moving forward with a conditional commitment for a loan guarantee, in the fall of 2011, DOE proposed a two-year RD&D program for the project. DOE indicated that USEC’s application for a DOE loan guarantee would remain pending during the RD&D program but has given USEC no assurance that a successful RD&D program will result in a loan guarantee. Additional capital beyond the $2 billion of DOE loan guarantee funding that USEC has applied for and USEC’s internally generated cash flow will be required to complete the project. USEC has had discussions with Japanese export credit agencies regarding financing up to $1 billion of the cost of completing the ACP, with such potential financing predicated on USEC receiving a DOE loan guarantee.

USEC also expects to need at least $1 billion of capital for the project in addition to the DOE loan guarantee and the Japanese export credit agency funding discussed above. The amount of additional capital is dependent on a number of factors, including the amount of any revised cost estimate and schedule for the project, the amount of contingency or other capital DOE may require as part of a loan guarantee, and the amount of the DOE credit subsidy cost that would be required to be paid in connection with a loan guarantee. USEC currently anticipates the sources for this capital to include cash generated by the project during startup, available USEC cash flow from operations and additional third party capital.  USEC expects the additional third party capital would be raised at the project level, including through the issuance of additional equity participation. USEC has no assurances that it will be successful in obtaining this financing and that the delays the Company has experienced will not adversely affect these efforts. USEC also is uncertain regarding the amount of internally generated cash flow from operations that USEC will have available to finance the project in light of the delays in deployment of the project and potential requirements for USEC’s internally generated cash flow to satisfy its pension and postretirement benefit and other obligations. The amount of capital that USEC is able to contribute to the project going forward will also impact USEC’s share of the ultimate ownership of the project, which will likely be reduced as a result of raising equity and other capital to deploy the project.

In order to increase the likelihood of a successful financing and deployment of the American Centrifuge project and USEC’s participation in such project, USEC is engaged with its advisors and certain stakeholders on alternatives for a possible restructuring of its balance sheet. A restructuring of USEC’s balance sheet could adversely affect the holders of USEC common stock through dilution or loss in value. However, USEC has no assurance regarding the outcome of any discussions USEC pursues with creditors or other key stakeholders.

On June 12, 2012, USEC and DOE entered into a cooperative agreement to provide cost-share funding for the RD&D program. The cooperative agreement provides for 80% DOE and 20% USEC cost sharing for work performed during the period June 1, 2012 through December 31, 2013 with a total estimated cost of $350 million. DOE’s total contribution would be up to $280 million and USEC’s contribution would be up to $70 million. The cooperative agreement is being incrementally funded, and $177.8 million of DOE funding has been provided as follows:

  • $87.7 million of funding was provided by DOE accepting title to quantities of depleted uranium that enabled us to release encumbered funds that were providing financial assurance for the disposition of this depleted uranium;
  • $45.7 million of funding was provided pursuant to the six-month continuing appropriations resolution passed by Congress and signed by the President on September 28, 2012;
  • $44.4 million of funding was provided in March 2013 by DOE transferring the SWU component of LEU that DOE previously acquired from USEC in exchange for the transfer of quantities of USEC’s depleted uranium to DOE.

As of December 31, 2012, USEC made qualifying American Centrifuge expenditures of $115.1 million. DOE’s pro-rata share of 80%, or $92.1 million, is recognized as other income in 2012.  Of the $92.1 million, $87.7 million has been received by USEC and DOE’s remaining funding share of $4.4 million is included in current accounts receivable as of December 31, 2012.

Funding from DOE beyond the $177.8 million in obligated funding has not yet been authorized and is subject to Congressional appropriations, Congressional transfer or reprogramming authority to permit the use by DOE of funds previously appropriated for other programs, or other sources available to DOE. There is no assurance that this additional funding will be made available. Although USEC has adjusted its program spending to accommodate changes to the timing and amount of federal funding, USEC remains on schedule and budget to complete the RD&D program by the end of 2013. The amount of federal funding made available to date is expected to fund RD&D program activities through June 15, 2013, and USEC will continue to work with Congress and the administration to fund the RD&D program through December 2013 and achieve the remaining program milestones.

The cooperative agreement includes technical milestones for the RD&D program. DOE has the right to terminate the cooperative agreement if any of the remaining technical milestones are not met. DOE also has the right to terminate the cooperative agreement if USEC materially fails to comply with the other terms and conditions of the cooperative agreement.  Failure to meet the technical milestones under the cooperative agreement could provide a basis for DOE to exercise its remedies under the 2002 DOE-USEC Agreement.

In addition, the cooperative agreement contains non-binding performance indicators that are designed to be achieved throughout the RD&D program and ensure that the RD&D program is on track to achieve the milestones and other program objectives. Although the performance indicators are non-binding, the failure to achieve a performance indicator could cause DOE to take actions that are adverse to USEC.

Centrifuge Demonstration Facility Virtual Tour

Explore the American Centrifuge Demonstration Facility where USEC is showing the technical readiness of its AC100 centrifuge machines