DMO formally delivers Joint Support Ship to Dutch Navy

24 September 2015
HNLMS Karel Doorman seen conducting replenishment-at-sea operations with the De Zeven Provincien-class air-defence and command frigate HNLMS Tromp. Source: Royal Netherlands Navy

The Netherlands Defence Material Organisation (DMO) formally handed over the 28,000-ton Joint Logistic Support Ship (JSS) HNLMS Karel Doorman to the Royal Netherlands Navy (RNLN) on 24 September.

The ceremony marked the successful completion of the majority of the ship's sea acceptance test programme, a DMO spokesperson said. Karel Doorman will now start its work-up trajectory, with a view to achieving full operational readiness by mid-2016.

Built by Damen Schelde Naval Shipbuilding yard in Vlissingen under a contract signed in December 2009, Karel Doorman was laid down in June 2011 and launched in October 2012. Before completion the ship found itself in 2013 declared surplus to requirements under austerity-driven defence budget cuts. The decision was reversed by the Dutch government and it officially entered service with the RNLN on 24 April 2015.

Following commissioning, the ship embarked on a nine-week deployment to Norway, Canada, the United States, and the Dutch Antilles where it conducted warm weather trials, and underwater and magnetic signature testing under DMO supervision. In addition to the DMO's test programme, Karel Doorman was used for replenishment at sea operations throughout the nine weeks, transport of equipment to the Dutch Antilles, and successful trials with a Bell-Boeing MV-22 Osprey tiltrotor aircraft. It also participated in the annual 'Hurricane Exercise' ('HUREX 2015'), demonstrating the versatility and potential of the ship, the spokesperson said.

Prior to commissioning, in November 2014 the ship also completed a three-month deployment to West Africa to deliver aid to Ebola-struck countries.

Want to read more? For analysis on this article and access to all our insight content, please enquire about our subscription options ihs.com/contact



(269 of 303 words)
By posting a comment you confirm that you have read and accept our Posting Rules and our Terms of Use of this site.

RELEVANT PROFILE LISTINGS

  • Agusta-Bell 212.

    Operational speed: 120 kt (222 km/h). Service ceiling: 15,000 ft (4,373 m). Range: 270 n miles (500 km). Role/Weapon systems: Assault (seven aircraft) and ASW/ASUW (11 aircraft); mainly deployed to escorts, but also shore-based. Sensors (ASW/ASUW): APS-705 radar; ASQ 13-B sonar; STAR SAFIRE II

  • Multipurpose Patrol Ships

    Fleetlist Programmes: The Pattugliatore Polivalente d'Altura (PPA) programme is for a class of six multipurpose offshore patrol vessels, with an option for a further four ships. Five are to be in a low-end configuration (patrol) and one in high-end configuration (combat). A modular design approach

  • Frosch II class (Type 109)

    Fleetlist Comment: Ex-GDR ships disarmed and transferred from Germany 25 August 1993. 5 ton crane amidships. In GDR service these ships had two twin 57 mm and two twin 25 mm guns plus Muff Cob fire-control radar. Both refitted at Rostock and recommissioned 25 April 1995. 37 mm guns fitted after

  • Introduction

    Notes: (1) It was announced in November 2014 that a new Coast Guard was to be established in order to consolidate resources and to simplify the command, control, and responsibilities of existing maritime agencies, including the Sea and Coastguard, Police, and Customs. The new force took effect in

  • KCR-40 class

    Fleetlist Comment: Three patrol vessels, based on the navy's KCR-40 patrol craft were launched in 2014 and had entered service by early 2015. A class of six is planned.