Goodwood junction upgrade home
The Goodwood Junction Upgrade separates the existing freight and Belair passenger lines from the Seaford line, removing the need for trains on either track to stop and give way. Construction of the rail underpass near Victoria Street lowers the Seaford line below ground level, with the freight and Belair lines above.
The project included new and upgraded rail infrastructure along with new pedestrian facilities for the community. In 2014, the project won the 'Category 4 Project Value ($20m - $75m) Award at the South Australian Civil Contractors Federation Earth Awards.
Project time frame
January 2013 - September 2013
Project cost
$110 million