Prospect Park New Flatbush Avenue Entrances Construction and Willink Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    1% complete

This project will reconstruct the Willink Entrance to Prospect Park and construct two new entrances: a new grand entrance and pedestrian bridge at the existing berm separating Flatbush Avenue from the Rose Garden, south of Grand Army Plaza, and a new minor entrance connecting Flatbush Avenue to the internal pathway east of the Dongan Oak Monument.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019
Completion Date: June 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $3,200,000
Funding Source: Mayoral

Location

Prospect Park , Brooklyn
Flatbush Avenue between Grand Army Plaza and Empire Boulevard

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project